BSC Construction Updates
                                                                     Updates will be posted regularly.
Link to Construction Updates Map
July 21, 2014

Crews will begin striping the parking lot lines today. They will begin with the lots that have concrete in them first and then do the asphalt lots after the crack sealing has been done.  It will take approximately 3-4 weeks to finish all the parking lots.



July 17, 2014

The Schafer Hall boiler change out will begin this week. There will be some parking spots blocked off in the Leach staff parking lot and Jack Science Center parking lot  for the contractors' dumpster and equipment. This is scheduled for a September 30 completion date. Also, new underground heating lines going from Schafer Hall to Werner Hall are being installed so areas will be blocked off while work is done on the underground piping. This portion of the project will be completed by the time classes start on August 26.

Starting July 21 Northern Improvement will be tearing up College Drive west of the Career Academy entrance all the way to Schafer Street intersection. This will last approximately 2 weeks.

The week of August 4 contractors will start installing new heating lines from the Schafer Hall boiler room through the link to Jack Science Center and down the 3rd floor hallway in Jack Science Center. The goal is to finish this before classes start Aug 26.

Contractors will also be saw cutting the south wall of the greenhouse in Jack Science Center starting the week of August 4 to install new windows later on.  This should be completed in approximately 1 week.



July 15, 2014

The Schafer Street paving project started July 14 and will continue for approximately two weeks.



July 9, 2014

Starting Thursday, July 10, Mariner Construction will be doing major asphalt repairs in the east Technical Center parking lot, Jack Science Center faculty parking lot and the big parking lot north of the digital BSC sign on the corner of Schafer Street and College Drive.  

Sections of, and possibly all of, these lots will be closed during repairs. Crews will begin with the big patches, move on to fix the smaller patches and then start crack sealing. Updates will posted with the progress of these projects.



June 25, 2014

During the week of June 30, Edwards Avenue will be closed from the corner of Schafer and Edwards up to the Armory as crews do the sanitary sewer tie-in to the new building. The road should open again by July 4.  

BSC's Student Life department will move to the basement level of the Student Union the first week of August and remain there until the remodeling of the Union is complete, approximately January of 2015. No meeting rooms will be available in the Student Union during this timeframe.



June 20, 2014

J E Dunn will be on site starting this Saturday and Sunday.  Glass Concrete Construction will be working Saturday and Sunday till noon for the next 5 weekends.



June 19, 2014

During the week of June 23, the city will be working on the water main and storm sewer lines on campus.

One lane of traffic on Edwards will be shut down while the work lasts. The city will  provide traffic control personnel and signage while the lane is closed.



May 30, 2014

During the dirt hauling process, crews will be cleaning the streets around the construction site daily.



May 28, 2014

For the next 3-4 days trucks will be hauling top soil and fill from the Communications and Creative Arts Center construction site to the northeast corner of the Tech Center parking lot. The dirt will be stockpiled there until it is returned to the site later in the process.



May 22, 2014

Parking on Friday, May 23 will be at a premium and traffic will be heavier than usual on campus as the MDU Resources Community Bowl hosts the state track meet.

On Tuesday May 27, the Student Union will be without power. Advisors and others with laptops will be working as they are able in a variety of locations that day and available via email, but not telephone.

Beginning May 27, workers will be hauling dirt out of the Communications and Creative Arts building site. Heavy truck traffic in and out of the building area can be expected for approximately two weeks. Drivers should exercise extra caution when navigating the area.



May 14, 2014

The public is invited to the groundbreaking of the BSC Communications and Creative Arts Center on Tuesday, May 20 at 1:30 p.m. at the corner of Edwards Ave. and Schafer St.



May 5, 2014

The Student Union will be closed on Tuesday, May 27 from 8 a.m. - 5 p.m. for electrical work.



April 16, 2014

The Leach Staff parking lot will be closed on Tuesday, April 22 due to lifting the HVAC equipment with the crane.

A temporary power route to provide electricity to the JE Dunn construction trailers will be put in place the week of April 28  and remain in place until June of 2015. See the map for more detail.



April 11, 2014
  • There will be NO parking in the Leach Music staff parking lot Monday, April 14. It will be blocked off to unload HVAC equipment. Starting Tuesday April 15 the corner next the Schafer Hall's boiler room will be closed off to stage the HVAC equipment until installation of the Chiller.
  • Soil boring/testing for the new housing east of Lidstrom  will begin the week of April 14.
  • Cleaning and sweeping of the parking lots will begin the week of April 14 also.
  • On April 21, workers will cone off the area in the Law Enforcement Center parking lot where the construction trailers will be located. The trailers are tentatively scheduled to arrive on April 23.
  • Temporary fencing is expected to go up on the Communications Center site around the 23rd also.



April 7, 2014

The Communications and Creative Arts Center groundbreaking will occur in April. In preparation:
  • Construction fencing will be put in place beginning the week of April 7.
  • The construction trailers will arrive on campus around April 15. They will be located in the parking lot west of the Law Enforcement Center throughout the life of the project.


Connect: Social Life TwitterFacebookYouTubeRSSiTunesFlickr
Accessibility   |   Campus Security   |   Copyright Act   |   Disclaimer   |   NDUS   |   Privacy Policy
Bismarck State College, P.O. Box 5587, 1500 Edwards Avenue, Bismarck, ND 58506     701-224-5400  ::   800-445-5073